1.     Area per computation does not tally with the area per title
Activity
Percentage
Cost
Procedure
1.1 Research
30 %

Inquire from LRA,LMB, LMS, CENRO, PENRO, Court, Archives, National Library, ROD, Municipal/City/Provincial Assessor, MPDO (secure certification as to non-availability of data), fellow private GEs
Research the names of the adjacent owners
1.2 Reconnaissance

10%

Identification of adjacent owners
Location of tie point, old points, PRS’92 points and other points with known geographic position
1.3 Conduct of Survey
30%

Issue Survey Notification Letter
Conduct of Perimeter Survey using hand held GPS (in case of tie line doubt)
Field Work: Use engr’s transit or total station in case of missing sides or blurred technical descriptions
Office Work: computation and cartographic works
Preparation of Sketch Plan (preferably 1:4000)
Request for pre-projection at the LMS
1.4 Preparation of Complete Survey Returns
5%

Office Work: Computation and cartographic works
1.5 Documentation
10%


1.6 Submission
5%


1.7 IVAS
10%



100%

For the 1st has. or fraction thereof


2.     Missing Side (three sides or more)
Activity
Percentage
Cost
Procedure
2.1.          Solution by three point problem
15%


2.2 Conduct of Survey
40%


2.3 Preparation of Complete Survey Returns
15%


2.4 Documentation & Submission
20%


2.5  IVAS
10%


TOTAL
100%
PhP 15,000.00

                                     
3.     Cannot be located on the ground(GFI,Foreclosed Properties)
Activity
Percentage
Cost
Procedure
3.1 Back Tracking of previous owner
10%


3.2 Boundary Computation and Geographic Position,
10%


3.3 Pre-projection at LMS
5%


3.4  Further research Based on the result of Pre-projection
10%


3.5 Encoding of Data gathered
10%


3.6 Conduct of Survey
25%


3.7 Preparation of Complete Survey Returns
10%


3.8 Documentation & Submission
10%


3.9  IVAS
10%


TOTAL
100 %
PhP


4.     Tie Point (no vailable geographic position)
Activity
Percentage
Cost
Procedure
4.1 research all adjoining lots or available approved survey plans.
10%


4.2 Secure certified Xerox copy of Titled properties
20%


4.3 Computation and Plottings of research data
10%


4.4 Conduct of Survey
30%


4.5 Preparation of Complete Survey Returns
10%


4.6 Documentation & Submission
10%


4.7  IVAS
10%


TOTAL
100%



5.     Old surveys not accepted during cadastral survey or nor reflected in the CM/PM
Activity
Percentage
Cost
Procedure
5.1 Secure certified true copy of title
10%


5.2 Researc h at Municipal/ City Assesors of Adjacent Lots
10%


5.3 Research Old Survey Plan (PSU,H, F,II, Etc.) at LMS and other offices
10%

Secure Certification from diff. agencies concerned
5.4 Computation and Plottings of researched  data
5%


5.5 Pre-projection at LMS
5%


5.6 Further research based on the result of Pre-projection
10%


5.7 Preparation of Complete Survey Returns
10%


5.8 Documentation & Submission
15%


5.9  Request for Reflection in the Cadastral Map
10%


5.10 Annotation at the back of the Title of the equivalent Cadastral lot
15%


TOTAL
100%
PhP




6.     Covered by previous survey
Activity
Percentage

Cost
Procedure
6.1 Conduct research of covering surveys
10%



6.2 Computation and Plottings of researched  data
10%


Prepare map into one system
6.3  Preparation of Complete Survey Returns
10%



6.4 Request for Reflection in the Cadastral Map
15%



6.5 Double check on the ground of the outcome of reflection of the previous survey
20%



6.6 Re-submittal of Complete Survey Returns
15%



6.7 Documentation & Submission
10%



6.8  IVAS
10%



TOTAL
100%
PhP