1. Area per computation does not tally with the area per title | |||
Activity | Percentage | Cost | Procedure |
1.1 Research | 30 % | Inquire from LRA,LMB, LMS, CENRO, PENRO, Court, Archives, National Library, ROD, Municipal/City/Provincial Assessor, MPDO (secure certification as to non-availability of data), fellow private GEs Research the names of the adjacent owners | |
1.2 Reconnaissance | 10% | Identification of adjacent owners Location of tie point, old points, PRS’92 points and other points with known geographic position | |
1.3 Conduct of Survey | 30% | Issue Survey Notification Letter Conduct of Perimeter Survey using hand held GPS (in case of tie line doubt) Field Work: Use engr’s transit or total station in case of missing sides or blurred technical descriptions Office Work: computation and cartographic works Preparation of Sketch Plan (preferably 1:4000) Request for pre-projection at the LMS | |
1.4 Preparation of Complete Survey Returns | 5% | Office Work: Computation and cartographic works | |
1.5 Documentation | 10% | ||
1.6 Submission | 5% | ||
1.7 IVAS | 10% | ||
100% | For the 1st has. or fraction thereof |
2. Missing Side (three sides or more) | |||
Activity | Percentage | Cost | Procedure |
2.1. Solution by three point problem | 15% | ||
2.2 Conduct of Survey | 40% | ||
2.3 Preparation of Complete Survey Returns | 15% | ||
2.4 Documentation & Submission | 20% | ||
2.5 IVAS | 10% | ||
TOTAL | 100% | PhP 15,000.00 |
3. Cannot be located on the ground(GFI,Foreclosed Properties) | |||
Activity | Percentage | Cost | Procedure |
3.1 Back Tracking of previous owner | 10% | ||
3.2 Boundary Computation and Geographic Position, | 10% | ||
3.3 Pre-projection at LMS | 5% | ||
3.4 Further research Based on the result of Pre-projection | 10% | ||
3.5 Encoding of Data gathered | 10% | ||
3.6 Conduct of Survey | 25% | ||
3.7 Preparation of Complete Survey Returns | 10% | ||
3.8 Documentation & Submission | 10% | ||
3.9 IVAS | 10% | ||
TOTAL | 100 % | PhP |
4. Tie Point (no vailable geographic position) | |||
Activity | Percentage | Cost | Procedure |
4.1 research all adjoining lots or available approved survey plans. | 10% | ||
4.2 Secure certified Xerox copy of Titled properties | 20% | ||
4.3 Computation and Plottings of research data | 10% | ||
4.4 Conduct of Survey | 30% | ||
4.5 Preparation of Complete Survey Returns | 10% | ||
4.6 Documentation & Submission | 10% | ||
4.7 IVAS | 10% | ||
TOTAL | 100% |
5. Old surveys not accepted during cadastral survey or nor reflected in the CM/PM | |||
Activity | Percentage | Cost | Procedure |
5.1 Secure certified true copy of title | 10% | ||
5.2 Researc h at Municipal/ City Assesors of Adjacent Lots | 10% | ||
5.3 Research Old Survey Plan (PSU,H, F,II, Etc.) at LMS and other offices | 10% | Secure Certification from diff. agencies concerned | |
5.4 Computation and Plottings of researched data | 5% | ||
5.5 Pre-projection at LMS | 5% | ||
5.6 Further research based on the result of Pre-projection | 10% | ||
5.7 Preparation of Complete Survey Returns | 10% | ||
5.8 Documentation & Submission | 15% | ||
5.9 Request for Reflection in the Cadastral Map | 10% | ||
5.10 Annotation at the back of the Title of the equivalent Cadastral lot | 15% | ||
TOTAL | 100% | PhP |
6. Covered by previous survey | ||||
Activity | Percentage | Cost | Procedure | |
6.1 Conduct research of covering surveys | 10% | |||
6.2 Computation and Plottings of researched data | 10% | Prepare map into one system | ||
6.3 Preparation of Complete Survey Returns | 10% | |||
6.4 Request for Reflection in the Cadastral Map | 15% | |||
6.5 Double check on the ground of the outcome of reflection of the previous survey | 20% | |||
6.6 Re-submittal of Complete Survey Returns | 15% | |||
6.7 Documentation & Submission | 10% | |||
6.8 IVAS | 10% | |||
TOTAL | 100% | PhP |